Energy networks
The grid is the new bottleneck
The energy transition's constraint has moved from generation to networks. What that means for investment, delivery and the firms that build them.

The short answer
Renewable generation is no longer the hard part. Connecting it is. Global grid investment needs to roughly double this decade, and Australia faces the same pressure with longer distances and rising build costs. Network owners that plan ahead for capital, supply chain and workforce will set the pace for everyone else.
2x
increase in annual grid investment needed by 2030 (IEA)
1,500 GW
of renewables in advanced grid connection queues (IEA)
25-55%
real increase in Australian transmission cost estimates (2025 ISP cost update)
What did we say in 2021?
In January 2021 we argued that Australia's National Electricity Market was built for a different era. The network was designed to move power from a handful of large coal stations to the cities. New wind and solar farms were appearing in regional areas, often exactly where the transmission network was weakest and oldest. Renewables had already lifted total generation capacity in the market from about 40 GW to 60 GW since 2007.
AEMO's 2020 Integrated System Plan made the same point in its own language. It flagged urgent transmission investment to avoid price spikes and reliability problems, and listed a set of actionable projects, including a new 330 kV interconnector between South Australia and New South Wales, a 500 kV upgrade to the southern New South Wales network, and links to new renewable energy zones. Five years on, that argument has become the central story of the transition worldwide.
Why has the bottleneck moved to the grid?
For a decade the question was whether wind and solar could compete on cost. That question is settled. Renewables now account for the large majority of new power capacity added globally each year. The new question is whether networks can connect that generation fast enough, at a cost customers will accept.
The International Energy Agency has been blunt about the answer. Its analysis shows grid investment stuck at roughly US$300 billion a year while generation investment surged, and an enormous volume of renewable projects waiting in connection queues. To keep pace, annual grid investment needs to roughly double by 2030.
Annual investment in electricity networks, US$ billions
Source: IEA, World Energy Investment 2025; IEA, Building the Future Transmission Grid 2025.
Three forces make this harder than simply spending more. Supply chains for transformers, cables and switchgear are stretched, with long lead times. Skilled workforces in high-voltage design and construction are thin. And planning and approval processes were designed for a slower pace of change.
The connection queue is the clearest symptom. The IEA estimates that at least 3,000 GW of renewable projects worldwide are waiting for a grid connection, about half of them at advanced stages. In several markets the wait for a connection now runs to years rather than months.
Equipment is the second symptom. The IEA reports that prices for cables and large power transformers have almost doubled since 2021, and waiting times for both have lengthened sharply. A network owner that orders late now joins the back of a global queue.
How is Australia different?
Australia shares the global pattern but faces compounding challenges: continental distances, a long and thin network, workforce concentration in a few cities, and a regulatory framework that was not designed for this pace of build. AEMO's Draft 2026 Integrated System Plan identifies around A$9 billion of actionable transmission projects across the market, and independent cost updates show transmission project estimates rising by 25 to 55% in real terms.
Demand is also changing shape. Electrification of transport and industry, and the rapid growth of data centres, mean networks must plan for load growth as well as new generation. That makes the timing of investment decisions more consequential than at any point in the past three decades.
Social licence is the other constraint. Several major Australian transmission projects have faced strong community opposition to routes through farmland, adding time and cost. Early, genuine engagement with landholders and Traditional Owners is now part of the critical path, not a box to tick after the route is chosen.
What do leading network operators do differently?
The operators moving fastest have shifted from a respond-and-connect posture to an anticipate-and-enable one. Instead of waiting for generators to apply for connection, they plan corridors ahead of demand, secure long-lead equipment early, and build the internal capability to deliver a much larger capital program.
- They make investment timing a board-level decision, not just a regulatory filing.
- They lock in supply chains through framework agreements and early procurement of long-lead items.
- They treat workforce as a strategic constraint, partnering with contractors and training providers years ahead.
- They work with regulators on faster, more flexible approval pathways, as the UK has done by accelerating a large group of strategic transmission projects.
What does this mean for leaders?
- Network owners: the window to secure supply chain capacity and skilled people at reasonable cost is closing. Decisions delayed today become more expensive tomorrow.
- Engineering and delivery firms: transmission is becoming one of the largest and longest-running markets in infrastructure. Capacity, specialist high-voltage skills and delivery partnerships will separate winners from the rest.
- Investors: regulated network returns are becoming more attractive as policy makers look for ways to bring private capital into grid build-out.
Frequently asked
Is Australia's challenge different from the rest of the world?
The drivers are the same, but distance, a thin network and a concentrated workforce make each project harder and more expensive to deliver.
What should a board ask its network team this year?
Which projects must be committed in the next two years, what long-lead equipment and skills they depend on, and what it costs to wait.
Will higher network spending raise power bills?
In the short term, network costs are passed through to customers, so regulators scrutinise every project. The case for investment rests on avoiding higher costs later, from congestion, wasted renewable output and reliance on expensive backup generation.
Sources
- International Energy Agency, World Energy Investment 2025
- International Energy Agency, Building the Future Transmission Grid, 2025
- International Energy Agency, Electricity Grids and Secure Energy Transitions, 2023
- AEMO, 2020 Integrated System Plan
- AEMO, Draft 2026 Integrated System Plan
- GHD and Amplitude Consultants, ISP Transmission Cost Database, 2025 update

About the author
Shan Vahora is the founder of SVZK Consulting. He advises leaders in infrastructure, energy and financial services on growth, M&A and market strategy, and previously worked at Strategy& (PwC), Cardno and Caterpillar. More about Shan
