Infrastructure

Why megaprojects fail, and how to beat the odds

Nine in ten megaprojects run over budget. The causes are well known, and so are the fixes. Most of them happen before the project is approved.

Shan VahoraShan Vahora, FounderFirst published Jan 2021 · Updated Oct 20267 min read
Highway interchange from above

The short answer

Most megaprojects overrun because costs and timelines are underestimated, and benefits overestimated, at the moment of decision. The fix starts before approval: independent business cases, forecasts grounded in what similar projects actually cost, and the discipline to stop or reshape a project when the evidence changes.

9 in 10

megaprojects that go over budget (Flyvbjerg)

44.7%

average cost overrun on rail projects (Flyvbjerg et al.)

~8%

of global GDP spent on megaprojects each year (Flyvbjerg)

How big is the megaproject economy?

Megaprojects, usually defined as projects costing US$1 billion or more, are the backbone of modern infrastructure: rail lines, motorways, airports, energy systems and hospitals. Oxford professor Bent Flyvbjerg has estimated that global spending on megaprojects runs at US$6 to 9 trillion a year, about 8% of global GDP.

Governments lean on them heavily during downturns, as they did during the post-COVID recovery, because they create jobs and leave lasting assets. That makes getting them right one of the highest-value decisions in public policy and in the engineering industry.

How often do they go wrong?

Very often. Flyvbjerg's research across thousands of projects found that around nine in ten go over budget. An influential study of transport projects found average cost overruns of 44.7% for rail, 33.8% for bridges and tunnels and 20.4% for roads. Overruns have been found across countries, eras and project types, which tells us the cause is systematic, not bad luck.

Australia is no exception. Grattan Institute analysis of Australian transport projects found that large projects are much more likely to overrun, and that a small number of the very largest account for a large share of the total.

Flyvbjerg calls this the iron law of megaprojects: over budget, over time, under benefits, over and over again. In his data, only about one project in two hundred came in on budget, on time and delivered the benefits promised.

Why do they fail?

  • Optimism bias: planners consistently underestimate costs and timelines and overestimate benefits.
  • Strategic misrepresentation: when funding is competitive, there is pressure to present the most attractive numbers.
  • Long durations: the longer a project runs, the more exposed it is to scope changes, inflation and political change.
  • Lock-in: high early spending and public commitment make projects very hard to stop, even when the case weakens.
  • White elephants: some projects cost more to run and maintain than the value they return.

If the causes are so well known, why do overruns persist? Part of the answer is incentives. The people who champion a project are rarely the people held to account years later when the costs come in. Part is what Flyvbjerg calls uniqueness bias: planners see their project as one of a kind, and so ignore what happened on similar projects elsewhere. And part is speed. Once a date is announced, there is pressure to start construction before the design is mature, which is exactly when changes become most expensive.

What actually works?

The evidence points to a handful of practices that make a real difference, most of them early in a project's life.

  • Reference class forecasting: base cost and schedule estimates on what comparable projects actually cost, not on bottom-up optimism.
  • Independent business cases before announcement: once a project is announced, it becomes politically hard to change.
  • Stage gates with a real option to stop: define in advance what evidence would cause a pause or redesign.
  • Smart risk allocation: give each risk to the party best able to manage it, rather than pushing everything to contractors at a premium.
  • Strong governance and benefits tracking: a capable client-side team and a program office that tracks benefits as well as costs.

Flyvbjerg sums up the lesson as think slow, act fast. Spend longer in planning, where changes are cheap, so that delivery can be quick and predictable. Modular approaches, where a project is built from repeatable units such as standard stations, spans or panels, reduce risk further because teams learn and improve with every unit.

What should leaders ask before approval?

  • How does our estimate compare with what similar projects actually cost?
  • Who prepared the business case, and were they independent of the decision?
  • What would make us stop, and who has the authority to say so?
  • Which risks are we paying contractors to hold, and could we hold them more cheaply?
  • How will we measure whether the benefits we promised actually arrive?

Frequently asked

Is the problem worse for public or private projects?

Overruns are common in both. Public projects face more political lock-in; private projects face more pressure to show early returns.

Can digital tools help?

Yes, particularly for comparing estimates with past projects and tracking delivery in real time, but they do not replace honest early decisions.

What is reference class forecasting?

A method that estimates cost and time by looking at the actual outcomes of a group of similar past projects, then adjusting for the specifics of yours. It counters optimism by starting from what really happened elsewhere.

Sources

  1. Bent Flyvbjerg, What You Should Know About Megaprojects and Why, Project Management Journal, 2014
  2. Flyvbjerg, Holm and Buhl, Underestimating Costs in Public Works Projects, Journal of the American Planning Association, 2002
  3. Grattan Institute, Cost overruns in transport infrastructure, 2016
  4. SVZK Consulting, Why Megaprojects Fail, January 2021
Shan Vahora

About the author

Shan Vahora is the founder of SVZK Consulting. He advises leaders in infrastructure, energy and financial services on growth, M&A and market strategy, and previously worked at Strategy& (PwC), Cardno and Caterpillar. More about Shan

Highway interchange from above

Related case study

Strategy partner to a global mobility business through a growth cycle

Chess pieces on a board

Next insight

AI in engineering and consulting: from experiments to advantage

Customer paying by card

Related service

Why aren't customers converting?

Shaping a major program? Get the evidence right first.

Tell us the decision you are facing. You will get a short proposal with a firm estimate within 3 business days.

Request a proposalOr book a 30-minute call